Our Process
At MIL Design we serve as both the designer and the contractor 2in1 for design and built projects, ensuring strong collaboration across all stages of the design and build. The aim is to achieve the right aesthetics, functions, ‘vibes’ of the place and even down to the finer details such as fengshui requirements.
Through a participatory and collaborative relationship with the Client we work to understand expectations work towards achieving the final dream project.
1
Schedule a Chat
A 1-hour design feasibility consultation with our founders Mil or Edward. This can be done through VC online or in person at our office.
2
Let's Get Started
Signing of Design Contract to appoint us. Once appointed we will kick off with a 2-hour on-boarding design consultation meeting to finalize the client’s lifestyle concepts, preferred moods or styles, and any detailed requirements.
This is when we will need to fully understand the client’s lifestyle requirements from their dreams, needs, personal collections, hobbies, to fengshui requirements of each of their family member.
Design Meetings
3
On-going design meetings and design dialogues continue with the client where we will work on finalizing the concept, layout drawings and 3D renders for signoff
This is referred as Design Stage which normally takes 5 weeks
Specs & Cost Review
4
Final selection of the material selections, finishes, color codes
Costing review
This is also when we value engineer the designs by going back to the drawing board to finetune drawings in order to achieve a design and cost balance for the client’s sign-off
5
Construction Contract Signed
Signing of Construction Cost Contract
6
Fabrication
We execute fabrication detail plans and start material ordering. We review our fabrication plans with our carpenters, tradesmen and specialists to advise on any specialist elements of the project.
Trade Day –On-site measurements and Pre- Enter Site evaluation or Dilapidation report evaluation by our site team
7
Site Implementation
Mobilisation to site which includes protection laying and mobilizing our site team and equipment to site. Structural, wet works, electrical works, plumbing works, if any, commence
Cabinetry woodworks and joineries fabrication commences off-site to be delivered to site later for installation
All other contract works will take place simultaneously according to the agreed timeline
We will have weekly site meetings with the client to update progress and ensure quality checks
This is referred as the Mobilization and Site Implementation stage and will normally take 6-8 weeks depending on project complexities. More complex projects will take longer time
8
Inspection
Pre-Handover Inspection Day (nearing completion). We have a dedicated day to walk through site with the client and our site team to inspect any deficiencies and resolve them.
9
Handover
Hand-over, Issue final invoice and thank you!